How to find the bottleneck in a small production line

The bottleneck is the slowest step, and it sets how much the whole line can make. To find it, time every station per unit and compare each one with your takt time. The longest one is the bottleneck. Fix it first: an hour saved there is an hour for the whole line, while an hour saved anywhere else is just more waiting.

The signs

Signs point you in the right direction, but timing tells you for sure. Sometimes the pile-up sits in front of a station that’s waiting on parts, not one that’s slow.

1. Figure your takt time

Takt time is how often you need to finish one unit: available working time ÷ units needed. Use the takt time calculator. It gives you the line every station needs to beat.

2. Time each station per unit

Prop a phone where it sees one station and film 3 or more full cycles, then do the next station. Time how long each station takes per unit, including the small tasks that happen every few units (refilling, swapping a roll of labels). Use the same unit for every station: per case, per part, per order.

3. Compare with takt

Divide each station’s time by takt time. Over 100% can’t keep up. The highest one is your bottleneck, and the line can make at most: available time ÷ that station’s time.

StationSeconds a case% of takt (500 s)
Prep jars and wicks38076%
Pour30060%
Trim, lid and label540108%
Pack and ship31062%

Here trim, lid and label is the bottleneck. The line can make 27,000 ÷ 540 = 50 cases a day against a need of 54.

4. Fix it, in this order

  1. Never let it wait. Stage materials so the bottleneck never runs out, and stagger breaks so it keeps running when others stop. An idle minute there is a minute the whole line loses.
  2. Move work off it. Give a task to a station with spare time. In the example, lidding moves to packing.
  3. Make it faster. Jigs, pre-cut materials, tools within reach, fewer steps.
  4. Add capacity last: another person, a second shift or equipment. These cost the most, so try the first three before you pay for them.

5. Expect it to move

Once you fix one bottleneck, the next-slowest station becomes the new one. In the example, after a label jig and moving lidding, trim and label drops to 340 seconds and packing, now at 370 seconds, sets the pace: 27,000 ÷ 370 = 73 cases a day. That’s fine as long as it’s under takt. Re-time after every change.

See the full example, with the layout, line-balance chart and staffing plan, in the Operations Package sample report.