At most small shops, the slow part of packing isn’t packing. It’s finding the items and handling the paperwork. In our example, a 2-minute-5-second order lost more than a third of its time to searching and the packing slip. Batch picking, a reach-based layout and prepping packaging first brought it to about 1:20 to 1:40.
Where the time goes
Film a few orders at your packing desk and time each step. In our example (a small gift shop, one packer):
| Step | Seconds | What’s going on |
|---|---|---|
| Read slip and pick items | 35–45 | Flipping through a sorter, walking to a crate |
| Set out packaging | 10–15 | Folding the box |
| Handle the packing slip | 10–15 | Picked up and moved 3 to 4 times |
| Wrap, seal, close | 60–80 | The actual packing |
| Clear the desk | 5–10 | Moving the order off |
7 changes, cheapest first
- Batch pick. Print a pick list for the day (or the morning), pick everything in one pass and put each order with its slip in a small tray. Packing then starts with everything in hand.
- Lay out by reach and order of use. Best sellers and packaging within easy reach (about 16 inches) of where you work, in the order you use them. Slow sellers go off the desk.
- Prep packaging before you start. Fold the day’s boxes, cut tissue to size and set up a weighted tape dispenser.
- Handle the slip once. Use it as a checklist: tick items as they’re wrapped, then put it in the box. That’s your final check too.
- Fewer box and mailer sizes. Two or three standard sizes mean less deciding and less hunting.
- Print shipping labels in a batch, not one at a time between orders.
- Check before you seal. A missing item costs far more than the seconds it takes to check.
Measure it
Film a few orders before and after the changes and time them the same way. In the example, the first three changes took a typical order from about 2:05 to about 1:20 to 1:40. At 300 orders a week and $26 an hour (wages plus benefits), that’s 2 to 3.75 hours a week, or about $2,800 to $5,100 a year. Your numbers will differ; that’s why it’s worth timing.
The full example, step by step, is in the process review sample report.

Reviewed by Randy Lipscomb, owner of Jively Consulting. Industrial and systems engineering degree from an accredited, nationally ranked program, with 20+ years of industry experience, most of it running production.