Takt time: what it is and how to figure it

Takt time is how often you need to finish one unit to keep up with demand. Takt time = available working time ÷ units needed. If a line has 27,000 seconds of working time a day and needs 54 cases, takt time is 500 seconds: one case every 8 minutes 20 seconds. Any station that takes longer than that can’t keep up.

Takt time calculator

Station times (optional)

Seconds per unit for each station or person. Leave blank to skip.

500 sec
takt time: one unit every 8 min 20 sec
27,000 seconds of working time a day

For planning only. Numbers are worked out in your browser and not sent anywhere.

How to figure takt time

Takt time = available working time ÷ units needed in that time

  1. Available working time: shift length minus planned breaks, lunch and meetings, times the number of shifts. An 8-hour shift with 30 minutes of breaks is 7.5 hours, or 27,000 seconds. Don’t subtract breakdowns or waiting: those are problems to fix, not planned time.
  2. Units needed: what customers need in that same period. Use the same period for both (a day and a day, or a week and a week).
  3. Divide. 27,000 seconds ÷ 54 cases = 500 seconds per case.

Takt time vs. cycle time

Takt time comes from your customers: how fast you need to go. Cycle time comes from your process: how long each station or person actually takes per unit. Comparing the two tells you where you stand:

A worked example

A four-station candle line needs 54 cases a day and has 27,000 seconds of working time, so takt time is 500 seconds. Its stations take 380, 300, 540 and 310 seconds a case. Trim and label, at 540 seconds, is 108% of takt: the line can make only 27,000 ÷ 540 = 50 cases a day and works overtime to catch up. After a label jig and moving one task to packing, the slowest station takes 370 seconds (74% of takt) and the line can make 73 cases a day. The Operations Package sample walks through it.

Common mistakes

Randy Lipscomb

Reviewed by Randy Lipscomb, owner of Jively Consulting. Industrial and systems engineering degree from an accredited, nationally ranked program, with 20+ years of industry experience, most of it running production.