Takt time is how often you need to finish one unit to keep up with demand. Takt time = available working time ÷ units needed. If a line has 27,000 seconds of working time a day and needs 54 cases, takt time is 500 seconds: one case every 8 minutes 20 seconds. Any station that takes longer than that can’t keep up.
Takt time calculator
Station times (optional)
Seconds per unit for each station or person. Leave blank to skip.
For planning only. Numbers are worked out in your browser and not sent anywhere.
How to figure takt time
Takt time = available working time ÷ units needed in that time
- Available working time: shift length minus planned breaks, lunch and meetings, times the number of shifts. An 8-hour shift with 30 minutes of breaks is 7.5 hours, or 27,000 seconds. Don’t subtract breakdowns or waiting: those are problems to fix, not planned time.
- Units needed: what customers need in that same period. Use the same period for both (a day and a day, or a week and a week).
- Divide. 27,000 seconds ÷ 54 cases = 500 seconds per case.
Takt time vs. cycle time
Takt time comes from your customers: how fast you need to go. Cycle time comes from your process: how long each station or person actually takes per unit. Comparing the two tells you where you stand:
- A station over 100% of takt can’t keep up. It’s your bottleneck, and it sets how much the whole line can make.
- Stations far under takt have spare time. Work can sometimes move from the bottleneck to them.
- Total work ÷ takt gives the fewest people the job could take if the work were split perfectly. Real lines need a little more.
A worked example
A four-station candle line needs 54 cases a day and has 27,000 seconds of working time, so takt time is 500 seconds. Its stations take 380, 300, 540 and 310 seconds a case. Trim and label, at 540 seconds, is 108% of takt: the line can make only 27,000 ÷ 540 = 50 cases a day and works overtime to catch up. After a label jig and moving one task to packing, the slowest station takes 370 seconds (74% of takt) and the line can make 73 cases a day. The Operations Package sample walks through it.
Common mistakes
- Counting lunch as working time. It makes takt look easier than it is.
- Mixing periods, such as weekly demand with daily hours.
- Treating takt as a speed target for people. It’s a planning number. Meet it by balancing the work, not by asking people to rush.
- Not updating it. When demand changes, takt changes. Busy season can turn a comfortable line into one with a bottleneck.

Reviewed by Randy Lipscomb, owner of Jively Consulting. Industrial and systems engineering degree from an accredited, nationally ranked program, with 20+ years of industry experience, most of it running production.