A time study tells you how long a job should take at a normal pace, with normal breaks and interruptions. You can do a simple one with a phone video: film 5 to 10 cycles, break the job into steps, time each step, adjust for pace and add an allowance. In our example, an order-packing job works out to 2 minutes 24 seconds per order, about 25 orders an hour.
What a time study is for
A time study turns “it takes a while” into a number you can plan with. Owners use it to:
- Quote and schedule: know how many units a person can finish in a day.
- Staff: figure how many people a busy season needs.
- Set fair targets: give new hires a goal based on a normal pace, not your fastest person.
It doesn’t tell you what to change. It measures the job as it’s done today. (Finding what to change is what a process review adds.)
1. Pick one job and tell your team
Choose a job that repeats many times a day or week: packing an order, assembling a part, plating a dish, servicing a car. Tell the person you’re filming what you’re doing and why. People speed up or slow down when they feel judged, and a study of an unusual pace isn’t worth much. Everyone on camera should agree to be filmed.
2. Film it well
- Hold the phone still on a tripod or shelf, turned sideways.
- Show the whole work area, including where materials come from and where finished work goes.
- Film 5 to 10 full cycles in one take. No editing or speeding up. More cycles give a better average.
- Film a normal day, with your usual worker and usual mix of work.
3. Break the job into steps
Write down each step (time-study people call them elements) with a clear start and end you can see on video. “Starts when she picks up the slip, ends when the first item is on the desk” is clear. “Getting ready” isn’t. Keep steps between about 5 and 60 seconds long so they’re easy to time.
For packing an online order, the steps might be: read the slip and pick the items, set out packaging, handle the slip, wrap, seal, close the mailer and clear the desk.
4. Time each step
Play the video back and write down the time on the player at the start and end of each step, for every cycle. Subtract to get each step’s time, then average each step across the cycles. A spreadsheet makes this quick. Note anything unusual (a dropped item, a phone call) and leave it out of the average, but keep a list: if it happens often, it’s part of the job.
5. Adjust for pace
If the person on video works faster or slower than a trained person at a steady, sustainable pace, adjust that step’s time with a rating. 100% means normal pace; 105% means a little faster than normal, 95% a little slower.
Normal time = observed time × rating
Rating takes judgment. When in doubt, use 100% and say so.
6. Add an allowance
Nobody works every second of a shift. An allowance covers personal time, fatigue and small delays. Many shops use somewhere around 10% to 20%; our example uses 15%.
Standard time = normal time × (1 + allowance)
7. Turn it into capacity
Units per hour = 3,600 ÷ standard time in seconds
Multiply by the paid working hours in a shift for units per shift. Divide your daily demand by units per shift to see how many people the job needs.
A worked example
Ten orders were timed at a small online shop’s packing desk:
| Step | Observed | Rating | Standard (15%) |
|---|---|---|---|
| Read slip and pick items | 34.4 s | 95% | 37.6 s |
| Set out packaging | 11.6 s | 100% | 13.3 s |
| Handle the packing slip | 10.9 s | 100% | 12.5 s |
| Wrap items | 30.8 s | 105% | 37.1 s |
| Seal | 15.7 s | 100% | 18.1 s |
| Close in mailer | 15.1 s | 100% | 17.4 s |
| Clear the desk | 6.5 s | 100% | 7.5 s |
| Per order | 125.0 s | 143.5 s |
143.5 seconds is 2 minutes 24 seconds per order. 3,600 ÷ 143.5 = 25 orders an hour, or about 188 in a 7.5-hour shift. At 60 orders a day, packing takes about 2.4 hours, so one person part of the day covers it. At 400 orders a day in the holidays, it takes 3 packers.
Common mistakes
- Too few cycles. One or two cycles hide the normal ups and downs.
- Timing your fastest person on their best day. Use a typical person and adjust with a rating.
- Mixing very different jobs. A one-item bag and a five-item gift box are two jobs. Time them separately or pick the common one.
- Forgetting the once-a-batch work. Setting up, restocking and cleanup count too. Time them and spread them over the batch.
- Leaving out the allowance. Without it, targets are too tight and people fall behind every day.

Reviewed by Randy Lipscomb, owner of Jively Consulting. Industrial and systems engineering degree from an accredited, nationally ranked program, with 20+ years of industry experience, most of it running production.